A Fuzzy Approach for Generalized Project Selection and Scheduling Problem with Resource Management
Abstract
In this study, the problem of project selection and scheduling with resource management is considered project setup times, dynamic project arrivals, priorities and relationship between projects. A fuzzy multi-objective mixed integer linear programming (MILP) model is proposed for the solution of the problem. The classic two-phase fuzzy goal programming (FGP) approach is modified to solve the proposed multi-objective MILP model. The addressed problem is defined over the project selection and scheduling problem of a construction company. The effect of resource management on the project selection and scheduling problem is demonstrated over the generated test problems. Modified two-phase FGP and classic two-phase FGP approaches are compared over test problems. With the use of the modified two-phase FGP approach, additional alternative solutions are found for the problem.
Keywords
Kaynakça
- [1] Z. Chen, Y. Lan, R. Zhao, C. Shang, Deadline-based incentive contracta in project management with cost salience. Fuzzy Optimization and Decision Making 18 (2019) 451-473.
- [2] A. RezaHoseini, S.F. Ghannadpour, M. Hemmati, A comprehensive mathematical model for resource-constrained multi-objective Project portfolio selection and scheduling considering sustainability and projects splitting. Journal of Cleaner Production 269 (2020) 122073.
- [3] X. Li, Y. Wang, Q. Yan, X. Zhao, Uncertain mean-variance model for dynamic project portfolio selection problem with divisibility. Fuzzy Optimization and Decision Making 18 (2019) 37-56.
- [4] H. Ke, W. Ma, J. Ma, Solving project scheduling problem with the philosophy of fuzzy random programming. Fuzzy Optimization and Decision Making 11 (2012) 269-284.
- [5] M. Shariatmadari, N. Nahavandi, S.H. Zegordi, M.H. Sobhiyah, Integrated resource management for simultaneous Project selection and scheduling. Computers and Industrial Engineering 109 (2017) 39-47.
- [6] R. Khayamim, S. Shetab-Boushehrib, S. Hosseininasab, H. Karimi, A sustainable approach for selecting and timing the urban transportation infrastructure projects in large-scale networks: A case study of Isfahan, Iran. Sustainable Cities and Society 53 (2020) 101981.
- [7] R. Mahmoudi, S. Shetab-Boushehri, S.R. Hejazi, A. Emrouznejad, P. Rajabi, A hybrid egalitarian bargaining game-DEA and sustainable network design approach for evaluating, selecting and scheduling urban road construction projects. Transportation Research Part E 130 (2019) 161-183.
- [8] M.A. Coffin, B.W. Taylor, R & D project selection and scheduling with a filtered beam search approach. IIE Transactions 28 (2) (1996) 167-176.
Ayrıntılar
Birincil Dil
İngilizce
Konular
Mühendislik
Bölüm
Araştırma Makalesi
Yazarlar
Gülçin Bektur
*
0000-0003-4313-7093
Türkiye
Yayımlanma Tarihi
30 Haziran 2022
Gönderilme Tarihi
9 Haziran 2021
Kabul Tarihi
25 Şubat 2022
Yayımlandığı Sayı
Yıl 1970 Cilt: 6 Sayı: 1
APA
Bektur, G. (2022). A Fuzzy Approach for Generalized Project Selection and Scheduling Problem with Resource Management. Aksaray University Journal of Science and Engineering, 6(1), 1-16. https://doi.org/10.29002/asujse.950133
Cited By
Association Coefficient Measure of Intuitionistic Fuzzy Graphs with Application in Selecting Best Electric Scooter for Marketing Executives
Journal of Intelligent & Fuzzy Systems: Applications in Engineering and Technology
https://doi.org/10.3233/JIFS-222510